Plantrooms and Switch rooms coordination

Our bread and butter

MEP systems are complex in nature and require a multi-disciplined approach. Plant rooms and switch rooms have a number of considerations to be coordinated with certainty and success.

  • Some Common principles applied to our plant room coordination:

  • Access to components in congested areas (dampers, valves, instruments etc)

  • Minimum clearance zone for panels – typically 1000mm

  • Maintaining headroom clearance

  • Maintaining walkways for plant replacement strategies

  • Filter and Component replacement clearance zones

  • Coordination of lifting beams (where required)

  • Coordination of equipment layouts and plinth construction

  • Shared support system (coordination of floor-standing supports if required)

  • Verification of coordination with Vendors (if required)

  • Accounting for the bending radius of cables into panels.

Our in-house expertise regularly designs, constructs, and commissions complex MEP systems from inception to completion. We understand the need for practical design for plant areas and getting the installation right the first time.