Plantrooms and Switch rooms coordination
Our bread and butter
MEP systems are complex in nature and require a multi-disciplined approach. Plant rooms and switch rooms have a number of considerations to be coordinated with certainty and success.
Some Common principles applied to our plant room coordination:
Access to components in congested areas (dampers, valves, instruments etc)
Minimum clearance zone for panels – typically 1000mm
Maintaining headroom clearance
Maintaining walkways for plant replacement strategies
Filter and Component replacement clearance zones
Coordination of lifting beams (where required)
Coordination of equipment layouts and plinth construction
Shared support system (coordination of floor-standing supports if required)
Verification of coordination with Vendors (if required)
Accounting for the bending radius of cables into panels.
Our in-house expertise regularly designs, constructs, and commissions complex MEP systems from inception to completion. We understand the need for practical design for plant areas and getting the installation right the first time.
BIM: Industrial
Contact us
Get in touch to find out how we can support your next project.
Fill in the form and a member of our team will get back to you shortly.

