Commissioning
Intelli-Eng delivers comprehensive commissioning services designed to ensure that complex engineering systems are installed, tested, and operate exactly as intended. We provide a structured, end-to-end approach that fully integrates commissioning with engineering and project management from the outset.
Cleanrooms
-
CQV manager placement
HVAC balancing packages
Integrity testing of HEPA filters
Space classification & particle counting
Light & sound testing
Pressure cascade set-up and documentation
Temperature & relative humidity mapping
Microbiological testing
Calibration of CAVs / temperature / and relative humidity gauges
Team certified to CTCB-I standard
-
CQV management to ISO 14644
Preparation of the Room Book
Installation qualification & documentation
Operation qualification and documentation
Performance qualification
Certified equipment
-
Start to finish ownership for the mechanical testing on-site
Review design ensure flush ability review has been carried out according to BG29 or VIDI 6044/2035
Obtain, manage, and organise pre-start checklist from suppliers for Vendor start-ups and SATs.
Manage water fill for hydraulic testing – VDI 2035 / 6044 standard (ph, oxygen, conductivity, hardness) and documentation
Own sampling and analysis plan.
Manage and document any replenishment
Author flushing procedure according to VDI 6044 / 2035 system fill and dynamic flush to BSRI
Support Flushing – sizing & procurement of temporary pump rig
Filtration documentation for client witnessing & Signoff (Mag filtration, Filter filtration, Strainers & Fine filtration)
Coordinate works with building automation contractor
FAT Testing where required
Heat Load deployment for Chiller Load testing & IST support (If applicable)
Commissioning Schedule production, management & coordination – inputting into the larger schedule
-
Single Phase Floor Standing Heaters – 3KW – For Low Delta T’s
9KW 15KW, & 22KW - 3-PhaseFloor standing heaters– Plugged into Temporary PDU or Client’s Power Supply
Temporary Racks for Data Centres – Heat Emulators to Match RACK & IT level
Single phase: 2kw & 3kw floor standing heaters for smaller data centres, building without racks and IT areas
3 phase: floor standing heaters: 9kw, 15kw and 22kw direct plug-ins for electrical load testing and basic environmental tests when infrastructure not finalised
Stackable floor standing emulators: 10kw stackable and 20kw towers to simulate 800mm IT racks
Temporary racks: recreate final layouts with with rack-mounted heat load and server emulators installed.
-
Hydraulic flushing rig hires
Water / Glycol fluid options
BSRIA BG29 Method
Flow rates up to 350 L/S – for chilled water mains flushing on data centres.
Integrated dosing pots
Dual filtration for magnetic and non magnetic impurities down to 1µ
High gloss filter housing
Pump run dry prevention integrated safety
PLC controls for automation control panel
Booster options available for larger pipework up to 300mm
Custom ordering
-
IVDI 2035-1 and 2 Austrian Standard H5195-5
Service includes cooling & heating water treatment up to 10M3
Max 560 µs
1µ fine filtration
Filter set removal and fine filtration
Magnetic particle removals
Waste disposal
Connection Implementation
Documentation
System fill attendance if required
On site conductivity & PH testing
-
Internet-connected sensors collect real-time environmental testing data
Live on-site or remotely accessed information
Early issue identification and resolution expediate commissioning
Cloud based data storage for easier reporting and commissioning
Improved environmental performance
Reduced risk and lower expenditure
-
CQV management to ISO 14644
Preparation of the Room Book
Installation qualification & documentation
Operation qualification and documentation
Performance qualification
Certified equipment

